5 June 2026
Windows & doors in two, roofs on other two, awaiting windows to arrive & bricks arrive next week.
1 May 2026
Plywood bracing & iron on roofs for two, framing up for the next two.
27 Apr 2026
Trusses & roof framing on as well as the barge board iron.
17 Mar 2026
The hard work in preparing the foundations for number 3 & 4 done and concrete floor poured. Yay.
27 Feb 2026
Framing up on two, roof trusses ready & waiting.
10 Feb 2026
Concrete poured last week & boxing now off.
30 Jan 2026
Crikey, over a ton of reinforcing bars and mesh are in each slab.
15 Jan 2026
Work is continuing, polythene down and look at all that polystyrene insulation.
12 Dec 2025
The first two have started, foundations dug out, shutters up, gravel & crusher dust in along with plumbing.